Municipal Projects

Municipal Projects information center

Safe Routes to School and Traffic Calming
Project Start Date: January 18, 2021 (Phase 1)
Project Start Location:  Maple Ave between Washington and Homestead
Anticipated Project Duration: 4 months

Project Locations:
Phase 1 - Maple Ave at Washington, Frazier, Lawnside, E. Stiles, and E. Homestead - Start Date: Jan. 18
Phase 1- Lincoln Ave at Cedar and Washington - Start Date: Jan. 28
Phase 1 - Atlantic Ave at Lees, Edison, Coolidge, Dill, Curtis, Cooper, and W. Homestead - Start Date: Feb. 8
Phase 2 - Dill Ave from Stokes Ave to Atlantic Ave - Start Date: March 1
Phase 2 - Stokes Ave at Lees Ave and Lees Lane - Start Date: March 11
Phase 2 - Lees Lane from Stokes Ave to Linwood Ave - Start Date: March 18
Haddon Ave at Homestead Ave - Start Date TBA
Washington Ave at Maple Terrace - Start Date TBA
*Start dates are weather permitting


Work will include:
  • New ADA Curb Ramps
  • New Crosswalks
  • Signage
  • Intersection Bump Outs for traffic calming and pedestrian safety at Haddon/Homestead
  • New Drainage pipe and inlets
  • Decorative brick pavers
  • Select Concrete Roadway Slab Replacement
Meetings and recordings:
With questions contact:
Tim Staszewski - Borough Engineer
856-795-9595 x1094 | timothy.staszewski@rve.com

Cassandra Duffey - Borough Administrator
856-854-0720 x125 | cduffey@collingswood.com

The Safe Routes to School (SRTS) grant is a federal grant that promotes walking and bicycling to school through infrastructure improvements. Collingswood was awarded roughly $900,000 to make these improvements. Read more here.


Completed Projects:

Grant Avenue repaving project
Champion Ave to White Horse Pike (Rt 30)
Project Start Date: October 7, 2020
Anticipated Project Length: 4-6 weeks

Work will include:
  • Select tree removal
  • Trimming of dead tree branches.
  • Select curb, sidewalk, and driveway aprons
  • New ADA curb ramps
  • New inlet structures, grates, and curb heads
  • Select sump pump connection to the storm main
  • Removal of the existing roadway surface
  • Paving of the roadway with new blacktop
  • Planting of new street trees
  • Concrete crew will start on the even side of the street, near WHP, work towards Champion, then flip to the odd side
  • Access to properties will generally be maintained for the duration of the project

Grant Avenue repaving plans can be viewed here.